At TaskEnergy, we’re committed to helping social housing providers deliver safe, efficient and sustainable homes. The Cromford Mews project in Whaley Bridge exemplifies our hands-on, expert-led approach to decarbonisation and long-term energy resilience. This project saw the complete upgrade of outdated ground source heat pump (GSHP) systems across a sheltered housing complex, future-proofing homes while enhancing resident comfort and system reliability.
Objectives
The primary goal was to replace 42 ageing Calorex GSHP units, each nearing the end of their lifecycle.
These systems operated at a consistent 55°C but were externally housed, leaving them exposed to both weather-related wear and theft. After detailed heat loss assessments, each apartment was found to require under 4kW, providing a clear case for modernisation.
Our objective was to design and install internalised, efficient systems that would maintain existing performance levels while significantly reducing risk and improving operational efficiency.
Client: Sheltered Accommodation
Sector: Domestic
Duration: 3-year programme
Several key challenges shaped the project:
Weather exposure and security risks:
External units were vulnerable to environmental damage and theft.
Insulation limitations:
Original pipework boxing made proper insulation nearly impossible, raising concerns about efficiency and system lifespan.
Maintaining resident comfort:
Ensuring access to heating and hot water throughout each phase of the rollout was critical, particularly for vulnerable residents
Our solution
We delivered a tailored, unit-by-unit solution designed around the client’s needs.
-
Our aim was to replace aging GSHP units and upgrade end-of-life systems with modern, more efficient units. Since no prior monitoring data existed, we installed a heat meter to track energy extraction over 12 months, ensuring the ground temperature remained stable and that efficiency was not compromised.
-
We aimed to improve heating performance by installing variable speed GSHPs, which ran at lower speeds for longer periods, ensuring better temperature control and reduced energy consumption. Internalised systems drastically reduced heat loss and unit run-time, lowering operational costs.
-
We completed installations within four days per unit, maintaining continuous hot water availability for residents. A specialist team of two heat pump engineers and an electrician ensured swift installation with minimal disruption.
-
We provided the client with a complete project pack outlining full costings, timeline and scope of work. Installation was managed in close partnership with Key Integrated Services.
The results
Enhanced efficiency
Internalised systems drastically reduced heat loss and unit run-time, lowering operational costs.
Reliability and longevity
With all components protected indoors, maintenance needs and equipment failure risks were significantly reduced.
Improved peace of mind
Residents and asset managers now enjoy safer, quieter, and more efficient heating systems.
On time, on budget
Every installation was completed to schedule and within the approved financial plan.
Innovation & Efficiency
Future-proofing systems in older residential stock requires not just technical innovation but also sensitivity to resident needs. Our phased, low-disruption approach proved essential to maintaining trust and comfort throughout the project.
“TaskEnergy provided an innovative solution by moving the system indoors and installing a combined heat pump with in-built cylinder. This not only improved efficiency but also created valuable space for the tenant. Their technical expertise, attention to detail, and focus on resident comfort made them a partner we could rely on completely.” – Antony Ballone, Project Manager at Norse Group on behalf of High Peak Council
Built to deliver. Powered by purpose.
This project is a clear example of our purpose-led delivery, combining mechanical expertise with social value, ensuring that even complex decarbonisation efforts work for residents, not just regulations.